Noida Consumer Forum Orders Builder to Hand Over Flat After Cancellation

A Noida couple paid ₹7.5 lakh for a flat but faced cancellation after their ₹64 lakh home loan stalled due to missing builder documents, prompting consumer forum intervention.

  • The couple booked a 1,595 sq ft flat for ₹77.35 lakh and paid ₹7.5 lakh.
  • The builder allegedly failed to provide documents required for disbursing the ₹64 lakh home loan.
  • The consumer commission ordered possession within 30 days of receiving the remaining payment and awarded ₹5,000 in litigation costs.

Noida: A district consumer disputes redressal commission has directed JSS Buildcon Pvt Ltd and its two directors to hand over a flat to a Noida couple within 30 days after receiving the outstanding payment as per the builder-buyer agreement.

The order was passed on November 7 after the builder cancelled the allotment, citing non-payment, despite the buyers claiming that their home loan could not be disbursed because the required documents had not been provided by the company.

The case concerns Manoj Kumar Bhrigu and his wife, Niranjana Sharma, residents of Grand Ajnara Heritage in Sector 74, Noida. The couple booked a 1,595 sq ft apartment in a project developed by JSS Buildcon Pvt Ltd for ₹77,35,575. They paid ₹7.5 lakh towards the booking and subsequent demand, while arranging to finance the remaining amount through a bank loan.

The commission, headed by president Anil Kumar Pundir and member Anju Sharma, also directed the builder and its directors to pay ₹5,000 towards litigation expenses. The order was passed ex parte after the opposite parties failed to appear or submit a response to the consumer complaint.

Couple Paid ₹7.5 Lakh and Arranged a ₹64 Lakh Home Loan

According to the complaint filed on June 22, 2024, the buyers initially paid ₹1 lakh through cheque on July 7, 2023. They subsequently paid another ₹6.5 lakh on July 28, 2023, following a demand from the builder.

After the payments, a builder-buyer agreement was executed. The couple stated that they had agreed to clear the remaining amount in a lump sum through financing rather than making payments in instalments.

To arrange the purchase, they applied for a ₹64 lakh home loan from the Central Bank of India’s Shalimar Bagh branch in Delhi. The loan was processed on September 27, 2023, under a tripartite agreement involving the buyers, the builder and the bank.

The dispute reportedly arose after the bank sought additional documentation from the builder to release the approved loan amount.

On November 24, the bank’s representative, Rajat Mohan, reportedly emailed the builder informing it about the loan approval and requesting two documents required to complete the disbursement process.

However, according to the couple, the builder did not provide the documents despite repeated follow-ups by both the buyers and the bank. As a result, the ₹64 lakh loan could not be released.

The builder subsequently cancelled the apartment allotment, alleging that the buyers had failed to pay the outstanding amount.

The couple said they met the builder on April 25, 2024, and objected to the cancellation. They maintained that their agreed payment arrangement required them to pay the remaining amount in a lump sum through the bank loan and that the disbursement delay was caused by the builder’s failure to provide the required paperwork.

They also sent a legal notice on April 30, seeking resolution of the dispute. However, the notice reportedly received no response, prompting them to file a complaint before the district consumer commission on June 22, 2024.

The commission issued notices to JSS Buildcon and its directors, Pratosh Kumar Sharma and Ankit Sharma. However, neither the company nor the directors filed a written reply or appeared during the proceedings.

On May 8, 2025, the commission decided to proceed ex parte and examined the evidence and arguments submitted on behalf of the buyers.

While examining the case, the consumer commission noted that the buyers had already paid ₹7.5 lakh towards the apartment and that the builder-buyer agreement outlined the payment arrangement.

It observed that the home loan could not be disbursed because the builder had allegedly failed to provide the documents requested by the bank, despite repeated communications.

The commission concluded that the builder’s failure to facilitate the loan disbursement amounted to an unfair trade practice. It also held that cancelling the allotment on the grounds of non-payment, when the payment delay was allegedly linked to the builder’s own inaction, constituted deficiency in service.

The district consumer commission directed JSS Buildcon Pvt Ltd and its directors to hand over possession of the apartment within 30 days of receiving the balance payment in accordance with the builder-buyer agreement.

The opposite parties were also ordered to pay ₹5,000 towards the couple’s litigation expenses.

The order provides relief to the buyers by addressing the cancellation of their allotment and directing the builder to complete the handover process once the remaining contractual payment is received.

Also Read: Meesho CEO Buys Bengaluru Plots from BYJU’S Family for ₹83.8 Crore

Also Read: Greater Noida Authority Allots 6% Abadi Plots to 127 Farmers in Sirsa and Dadha

Get Early Updates Directly to Inbox!

SUBSCRIBE TO OUR NEWSLETTER AND GET UPDATED

We don’t spam! Read our privacy policy for more info.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button