Noida Builders Fined ₹2.33 Crore for Construction Dust and Pollution Control Violations

Authorities have imposed nearly ₹2.33 crore in penalties on Noida construction projects for dust-control violations, including non-functional anti-smog guns, uncovered materials and unauthorised work.

  • Around 75 penalties were imposed in Noida between September 30 and November 12.
  • Ivory County and Mahagun Infratech faced the highest individual penalties of ₹50 lakh each.
  • Greater Noida recorded around 60 recommended fines worth more than ₹1.5 crore.

Noida: Construction companies in Noida have faced penalties totalling nearly ₹2.33 crore for failing to follow prescribed dust-control and pollution prevention measures at their project sites. The action was taken between September 30 and November 12 as authorities intensified inspections amid worsening air quality across the National Capital Region (NCR).

Violations included uncovered construction materials, ineffective water sprinklers, non-functional anti-smog guns and construction activities continuing despite restrictions under the Graded Response Action Plan (GRAP).

According to official records, approximately 75 penalties were imposed across Noida during this period. October alone accounted for 47 challans worth around ₹1.3 crore against construction projects. Several violations were also reported in Greater Noida, where around 60 fines amounting to more than ₹1.5 crore were recommended between August 1 and November 14. Interestingly, the enforcement action also covered construction projects undertaken by the Noida Authority itself.

Two construction projects received the highest individual penalties of ₹50 lakh each.

The Ivory County project in Sector 115 was fined ₹50 lakh on October 5 after an inspection reportedly found construction materials stored in the open and ineffective water sprinkling arrangements. The action was taken before the strictest GRAP restrictions came into force.

Another ₹50 lakh penalty was imposed on Mahagun Infratech for its project in Sector 107 on November 12. According to an official, construction work was still taking place at the site despite GRAP Stage III restrictions, which prohibit most construction activities.

Three other projects were also recommended for penalties of ₹10 lakh each. These included Godrej Palm Retreat, Triune Global Solutions and Krescent Homes in Jaypee Greens Wishtown.

Inspections reportedly found four non-functional anti-smog guns and uncovered construction materials at the Godrej Palm Retreat site. At the Triune Global Solutions project, officials identified uncovered excavated soil and the absence of a tyre-washing facility, among other shortcomings.

In Greater Noida, authorities also recommended a ₹50 lakh penalty against Avaada Electro Private Limited following an inspection that identified violations of prescribed pollution-control requirements.

Officials have highlighted the importance of dust-control measures at construction sites, particularly during periods of severe air pollution.

A senior official said that inspections had identified several recurring problems, including construction materials left exposed to the air and water sprinkling systems that were not working effectively. Such practices allow dust to spread beyond project boundaries and contribute to deteriorating air quality.

The Uttar Pradesh Pollution Control Board (UPPCB) is also using digital monitoring systems to identify potential violations. Under the prescribed dust-control requirements, construction sites must register on the dust control portal and install Pan-Tilt-Zoom (PTZ) cameras.

Chudamani Nimbark, an Assistant Environmental Engineer with the UPPCB, oversees monitoring across 45 sectors, covering Sector 125 to Sector 168 in Noida. Her team reviews camera footage, records observations and identifies locations that require physical inspections.

The monitoring process involves checking registered construction sites through their camera links. Officials record observations such as whether construction is underway, whether a camera link is inaccessible and whether any suspicious activity requires further investigation. Teams subsequently visit the identified locations to verify violations on the ground.

The penalties come at a time when Noida is dealing with elevated levels of particulate pollution. Data from the Central Pollution Control Board (CPCB) showed that the average PM2.5 levels across Noida’s seven monitoring stations ranged between 104 and 206 micrograms per cubic metre over the preceding 30 days.

The national 24-hour standard for PM2.5 is 60 micrograms per cubic metre. Sector 62 recorded the highest average PM2.5 concentration at 206 micrograms per cubic metre, with peak readings reaching 365 micrograms per cubic metre.

PM10 pollution was also elevated. The reported average reached 315 micrograms per cubic metre, while the highest recorded peak was 496 micrograms per cubic metre. Sector 110 registered the second-highest PM10 peak at 393 micrograms per cubic metre.

Construction activities, uncovered soil, road dust and the movement of heavy vehicles can contribute to the spread of coarse particulate matter. These pollutants can further worsen air quality and increase exposure risks for residents.

Noida and Greater Noida moved through GRAP Stage I on October 21, Stage II on November 2 and Stage III on November 6, as air quality deteriorated.

Under the earlier GRAP stages, construction sites are required to follow dust-control measures such as:

  • Transporting construction and demolition waste in covered vehicles.
  • Installing and operating anti-smog guns wherever required.
  • Regularly sprinkling water to prevent dust from spreading.
  • Ensuring that construction materials and excavated soil are properly covered.
  • Providing tyre-washing facilities for vehicles entering and leaving project sites.

GRAP Stage III introduces stricter restrictions, including a ban on most construction and demolition activities, with limited exemptions for specified projects of national importance.

The UPPCB and other enforcement authorities are continuing their monitoring and inspection exercises across Noida and Greater Noida. Digital surveillance through PTZ cameras is being used to identify potentially non-compliant sites, followed by physical inspections where necessary.

Construction companies are expected to ensure that dust-control equipment remains operational and that all prescribed environmental safeguards are followed. Projects found violating the restrictions may face further penalties and enforcement action.

With air pollution remaining a major concern across NCR, stricter monitoring of construction and demolition activities will be important to prevent avoidable dust emissions and ensure compliance with GRAP requirements.

Also Read: UPPCB Sends Notices to 300 Housing Societies in Ghaziabad Over Air Pollution

Also Read: Faridabad Master Plan 2031: 3,100 Acres to Be Acquired for 6-Lane Roads and Green Belts Across 67 Sectors

Get Early Updates Directly to Inbox!

SUBSCRIBE TO OUR NEWSLETTER AND GET UPDATED

We don’t spam! Read our privacy policy for more info.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button